Our construction journey is complete!

We are excited to report that our longer-than-expected construction journey has been brought to a close. We completed the remaining construction activities (landscaping, the pergola, the pathway) in the summer of 2023 and received final approval from RVC based on the approved DP in the fall of 2023.

We have prepared a report to the community providing some history and answering some of the questions we have received. That report is available here.

A portion of the report is shown below:

 

Landscaping

The 2018 RVC DP includes the use of a landscaping design known as Xeriscaping. The architect and the geo-tech engineer developed this low maintenance landscaping design to comply with the DP condition that no potable water can be used for irrigation purposes; the geo-tech engineer also specified no irrigation on the west slope to ensure slope stability. Xeriscaping is a natural grassland that relies on rainwater for irrigation; the long grass that is a signature feature of xeriscaping is uncut. More information about xeriscaping and its environmental benefits is here:  https://en.wikipedia.org/wiki/Xeriscaping

The Landscape Plan also includes 182 trees and 519 shrubs, plus there is a natural grove of trees on the east side next to 12 Mile Coulee road.

Final Landscaping activities completed during the summer of 2023 include:

  • Planted the balance of trees and shrubs, including replacing any that had not survived.
  • Seeded or re-seeded grass in any bare areas.
  • Cleaned up landscaping adjacent to our neighbours.
  • Built up a portion of the earth berm on our south boundary.
  • Adjusted the rocks in the south rock swale.
  • Cleaned up and re-graded the gravel parking lot.
  • Repaired asphalt on the Regional Pathway.
  • Built the wooden pergola next to the building on the west side.

 

Ongoing Maintenance of the Landscaping

The contractor we hired to complete the final landscaping activities will continue to service the landscaping on the site.

After the vegetation has matured, the site will rely on rainwater to maintain the landscaping. The vegetation is not mature at this point; therefore, during the summer of 2023 we implemented a watering program to ensure the vegetation has the best chance to survive and thrive. Watering on the west slope will be limited to the trees and shrubs.

This watering program will remain in place for future years until we are satisfied that the vegetation is mature. We are committed to maintaining the landscaping long term. It will take several years for some of the vegetation, in particular the trees, to reach maturity.

 

We are here for you!

Many of our neighbours have come to see us for weekend services or other events and we are glad that you are reaching out to us. We are here for onsite spiritual teaching, serving people in need and community building. Our heart is to be a church in the community for the community – a place for you to explore the big questions in life without judgement, and to find meaning, belonging and friendships. Whether we are gathering online or in-person, we are here to journey through life with you.

We believe this construction project is so much more than a building. We represent a welcoming and compassionate addition to the neighbourhood where people can come for hope, purpose, community, and a place to have deep conversations about the big questions of life.

 

Construction Completion

It has been a challenging multiyear journey from construction to completion of our Bearspaw Campus facility. There have been delays, the most significant of which is the impact of the pandemic on the supply chain and trade availability. We are glad that our construction journey is complete.

This will be our final construction update; however we remain available to respond to any comments or questions you may have. If you have questions, please send them to build@cschurch.ca.

Alternatively, if you wish to speak with someone, call:

Communications Pastor Pamela Aramburu 403-520-6509

Previous updates

Your Questions & Feedback

Curious about the top feedback we have received to date and how we are incorporating it into our plans? Please click on the PDF link here.

To see more Frequently Asked Questions and Answers regarding the project, please click on the PDF link here.

As always, we are committed to keeping the lines of communication open with the community, during construction and beyond. If you have any questions, please contact us at communications@cschurch.ca or continue to check back here periodically to learn more about this exciting project.

A church in the community, for the community

Something exciting is about to happen in your community! Centre Street Church (CSC) is in the process of applying for a Development Permit for the construction of our Northwest Campus so we can better serve the community needs of Northwest Calgary.

Get Directions

This construction is more than just a building. It represents a welcoming community to strengthen relationships, serve the community, and provide people with a higher sense of purpose, as well as a safe space to explore the deeper conversations and big questions of life.

It’s a place to belong, grow, laugh and serve with others in ways that impact our neighborhood, our country, and our world.

Who We Are

Centre Street Church is one church in many locations, across five campuses with a heart to be in the community for the community. With over 60 years of history in Calgary, we are committed to bringing hope and help to people from all walks of life.

Our Bearspaw Campus opened in the fall of 2021 and we invite you to take a virtual tour here or stop by to see it for yourselves!

Join us for a service on Sundays at 9am or 11am

Did you know?

    • We provide needed community resources; our church facilities have supported local municipalities in many capacities from providing polling stations during elections to emergency reception centres during crises (e.g. 2013 Alberta Floods).
    • Every year Centre Street Church allocates millions of dollars to support organizations and communities that serve people in need in our communities, in our country and the world.
    • We are one of Canada’s only churches to provide faith-based emotional, spiritual and social support for over 250 people with special needs and their families.
    • We partner with compassionate service organizations to address the needs of marginalized communities (e.g. new Canadians, people in poverty, etc.)

Virtual Tour

Haven’t had a chance to check out CSC’s Bearspaw Campus? Check out our new virtual tour! We invite you to come and check us out in-person for a Sunday service!

 

Construction Details

For the last ten years we have been carefully working/consulting with Rocky View County; the Watermark community and the Land developer to obtain all regulatory approvals for the proper zoning for the property which will allow for a church facility.

In late 2017, we took ownership and received the title for these 10.91 acres of land. All of the deep engineering services on the land were completed in 2017.

Centre Street Church will strive to transition to your neighbourhood as smoothly as possible by committing to minimize any negative impacts through responsible practices and clear communication.

For example, construction mobilization, traffic and operations shall adhere to the industry standards.

Onsite Safety:

CSC has written and adopted a detailed construction safety program, following the OH&S industry standards and COR level requirements. This safety program shall be implemented and strictly adhered to by all site personnel and sub-contractors. CSC’s safety program clearly defines the responsibilities of all site personnel to maintain a safe job site for all workers and the public.

Communication:

As development can be challenging and complex, we commit to maintaining open communication with our surrounding communities and being attentive to issues as they arise throughout all construction phases and beyond.

If you have any concerns or questions as construction is underway, please don’t hesitate to contact us so we can address any issues as quickly as possible. Your feedback is important to us. You can reach us at: communications@cschurch.ca

Schedule and timeline:

Our tentative construction timeline is subject to change and includes the following:

1) Completion of the Construction Documents: Winter 2019.

2) Tender Process: Winter 2019

3) Construction Start: May 2019

Last updated March 19, 2019